We’re in the final stages of construction and we’re working hard to get ready for our June 10 Open House.

KidsCare Logo

Construction Update 5/15/2017

As you can see in the photos included in this update, this is an exciting time in the construction project. All of the glass is in and the block on the inside of the building is laid.

The drywall will be finished over the next couple of weeks and ready to paint.

The exterior cast stone veneer and brick is in the process of being laid which is starting to bring some color to the building.

In the school’s new gym (that will be shared-use space), the ceiling is painted and the base coat is on all the walls. The painters plan to finish next week. After that basketball goals and hardware will go in to the gym.

Beginning on June 1 the painters will start on the inside of the Club!

KidsCare Logo

April 11 photos

KidsCare Logo

Construction Photos as of April 5

We have just a few photos of the High School interactive room, the front counter check-in and parent area and the Middle School interactive room.

KidsCare Logo

Construction Photos from April 3, 2017

The latest updates to our building have been pretty exciting. As you walk around the inside of our building you will see that walls are going in as well as some plumbing. This week they installed the south stairwell and are getting the teen center mezzanine ready for concrete to be poured. Since our members are currently on Spring Break they have shut down the power at the school and are connecting a new transformer on-site to get us ready for the new power service.

We will have several different contractors working in the building over the next two weeks, running electric and data as well as getting the plumbing roughed in. If you drive by the building you will see that the building is currently being wrapped and framed with insulation. They have also made a lot of progress on the school’s new gym— you can see in the pictures all the walls are up, steel rafters are in and they have started to apply the roof.  Over the next two weeks they will be installing the membrane roof system over the gym and getting the roof drain systems in order as well.

In the club portion for the next two weeks they will be working on the internal walls as well as the concrete upstairs.

KidsCare Logo

Construction Photos as of March 13, 2017

*Hard Hats needed in some areas of the Construction Site*

Projected Completion Date: May 31st, 2017

  • Dining Wing
    • Kitchen Equipment On-Site – Finishing Plumbing before Final Set
    • LED Lights are On-Site – L&M Installing Outlets for them in Halo
    • Finishing Fire Suppression, Ceiling, and Paint
    • Doors Arriving Next Week
  • Education Wing
    • Drywall Finishing on 2nd Floor
    • Drywall Starting on 1st Floor
    • Primer, Paint, and Finish to Start Soon
    • Clouds for Area with Lights Selected and Ordered
    • Doors Arriving Next Week
  • Gym
    • New Flooring being quoted with SportCourt through DJ Construction
      • Flooring to be installed before Grand Opening
    • Lee Company to quote bleacher service and power
  • Exterior
    • Gym Storage
      • Foundation Poured
      • Block Walls in Next Couple Weeks
    • Garage & Woodshop
      • Plans Approved by Club
      • Waiting for Approval from City for Site Work
      • Pouring Footings and Floor Upon Final Approval
    • New Addition Gutters – Seamless will be installed
  • Submittals
    • None
  • Selections
    • Casework
    • Flooring for Entry Area
    • Flooring for Circulation Area
    • Paint for Entry Area
    • Paint for Circulation Area & Bathrooms
    • Paint for Learning Center & Teen Center
    • Counter Top for Entry Area
    • Camera Locations Updated
  • Change Orders
  • Questions or Concerns
    • Garage Plans
      • DJ Continuing talks with City of Goshen to ensure compliance with all regulations but also trying in every way possible to complete before Grand Opening.
      • Landscape Bond with City is required if 70% is not completed –
      • We do not want to come back in a disturb any new asphalt, concrete, or grass after the Grand Opening to finish garage/woodshop if possible.
    • Flooring in Teen Active Space
      • Use existing Gym Flooring in this space to save about $7,000 on Flooring
      • Update Prepared By: Tanner Pickett
KidsCare Logo

Construction Photos from March 2017

Our building project in Elkhart is now in full swing and the construction crews are working hard at getting it done and ready for our members. As you can see in the pictures we have all the external block walls up on the club side of the building and the roof has been put on the club and they currently have the steel infrastructure in place for the teen center mezzanine. Towards the end of the last week they finished up all the under slab plumbing rough-ins and were working on the inspections as needed as well as on Friday the 10th they poured the concrete floor. The current plan is for the school’s portion of this build to be done and operational at the beginning of August when school starts. At that point they will continue to demo and renovate the current school gym which will house the rest of our Club. It is currently on the schedule to turn the keys over to us in mid-November.