Construction Photos from March 2017

Our building project in Elkhart is now in full swing and the construction crews are working hard at getting it done and ready for our members. As you can see in the pictures we have all the external block walls up on the club side of the building and the roof has been put on the club and they currently have the steel infrastructure in place for the teen center mezzanine. Towards the end of the last week they finished up all the under slab plumbing rough-ins and were working on the inspections as needed as well as on Friday the 10th they poured the concrete floor. The current plan is for the school’s portion of this build to be done and operational at the beginning of August when school starts. At that point they will continue to demo and renovate the current school gym which will house the rest of our Club. It is currently on the schedule to turn the keys over to us in mid-November.